Garage Subpanel Calculator

Calculate feeder requirements for garage subpanels and detached building electrical service. Complete NEC Article 225 compliant calculations for safe, code-compliant installations.

NEC Article 225
Detached Buildings
Service Range
60A - 400A
Installation Types
Underground/Overhead
Applications
Garage, Shop, Barn

Detached Building Requirements

  • • Feeder disconnect required at detached building per NEC 225.31
  • • Equipment grounding conductor required with ALL feeders per NEC 225.30
  • • Grounding electrode system required if none exists at building
  • • Maximum 6 disconnects per building location per NEC 225.33
  • • Professional installation recommended - improper grounding can be deadly
Loading calculator...

Real-World Installation Examples

Standard 2-Car Detached Garage

100A subpanel, 75ft run, mixed loads

Load Breakdown: Lighting: 20A, Outlets: 40A, Garage Door: 15A, Welder: 50A

100A feeder, 2 AWG wire
6 AWG equipment ground
$1,850 materials + trenching
NEC 225.39, 225.30

Calculation Details:

Total Connected Load: 125A
Demand Calculation: 125A × 0.8 = 100A
Feeder Size: 100A minimum
Voltage Drop Check: 100A × 75ft × 2.6Ω/1000ft ÷ 240V = 8.1% (too high)
Upsize to 2 AWG: 100A × 75ft × 1.6Ω/1000ft ÷ 240V = 5.0%
Grounding: 6 AWG equipment ground required

Workshop with Heavy Equipment

200A subpanel, 100ft underground run

Load Breakdown: Table Saw: 30A, Dust Collector: 20A, Compressor: 40A, Welder: 60A, General: 50A

200A feeder, 250 kcmil wire
4 AWG equipment ground
$3,200 + underground installation
NEC 225.39, 310.15(B)(7)

Calculation Details:

Total Load: 200A nameplate
Demand Factor (industrial): 200A × 1.0 = 200A
Feeder: 200A service
Underground Run: USE-2 or RHW-2 required
Wire Size: 3/0 AWG copper (200A rating)
Voltage Drop: 200A × 100ft × 1.0Ω/1000ft ÷ 240V = 8.3%
Upsize: 250 kcmil → 6.7% drop
Grounding: 4 AWG equipment ground

Basic Garage with EV Charging

60A subpanel, EV charger + basic loads

Load Breakdown: EV Charger: 40A, Lighting: 15A, Outlets: 20A

80A feeder, 4 AWG wire
8 AWG equipment ground
$950 + EV outlet installation
NEC 625, 225.39

Calculation Details:

EV Charger: 40A continuous load
Basic Loads: 35A @ 75% demand = 26A
Total Demand: 40A + 26A = 66A
Feeder Size: 70A → use 80A standard
Wire Size: 4 AWG copper (85A capacity)
Grounding: 8 AWG equipment ground
Voltage Drop: Acceptable for typical runs

Detached Shop - 3-Phase Service

100A 3-phase, metal fabrication shop

Load Breakdown: Welder: 75A, Mill: 40A, Lathe: 30A, General: 55A

200A 3-phase, 3/0 AWG
4 AWG equipment ground
$4,500 + transformer costs
NEC 225.30, 430 motors

Calculation Details:

3-Phase Load Analysis:
Total Load: 200A per phase
Demand Factor: 200A × 0.85 = 170A
Balanced Load: 170A per phase
Feeder: 175A → 200A service
Wire: 3/0 AWG per phase + neutral
Grounding: 4 AWG equipment ground
Service Disconnect: 200A 3-pole

RV Garage with Multiple Services

Large garage, RV hookup + workshop

Load Breakdown: RV Service: 50A, Shop: 100A, Compressor: 30A, Welder: 60A

200A main + 50A RV
4 AWG + 8 AWG for RV
$3,800 + RV pedestal
NEC 225.33, 551.77

Calculation Details:

Multiple Services Analysis:
RV Service: 50A dedicated (NEC 551)
Shop Loads: 190A connected
Shop Demand: 190A × 0.8 = 152A
Main Feeder: 200A to handle both
Separate RV disconnect required
Feeder Wire: 3/0 AWG copper
Multiple disconnect rule: 6 max per NEC 225.33

Barn/Agricultural Building

Livestock facility, 150A service

Load Breakdown: Ventilation: 60A, Lighting: 30A, Outlets: 40A, Water: 20A

150A feeder, 1/0 AWG
6 AWG + supplemental
$2,800 + agricultural requirements
NEC 547 agricultural

Calculation Details:

Agricultural Load Calculation:
Total Connected: 150A
Demand Factor (ag loads): varies by type
Continuous Loads: Ventilation 60A × 1.25 = 75A
Other loads: 90A × 0.8 = 72A
Total Demand: 75A + 72A = 147A → 150A
Feeder: 1/0 AWG copper
Special: GFCI for wet locations
Grounding: Enhanced for livestock

NEC Article 225 - Detached Building Requirements

Feeder Disconnect

NEC 225.31

Disconnect required at building

Must disconnect all ungrounded conductors, rated for feeder load, lockable

Critical Safety

Service Entrance

NEC 225.32

Location of disconnect

Outside building or inside nearest point of entrance, readily accessible

Code Compliance

Maximum Disconnects

NEC 225.33

6 disconnect rule

Maximum 6 disconnects per building, each clearly marked

Safety & Code

Grouping of Disconnects

NEC 225.34

Grouped together

All disconnects must be grouped, exception for large buildings

Emergency Access

Grounding Requirements

NEC 225.30

Equipment grounding

Equipment grounding conductor required with feeder, sized per Table 250.122

Electrical Safety

Overhead Clearances

NEC 225.18

Minimum clearances

10ft min over driveways, 12ft over residential, 18ft over public areas

Physical Safety

Underground Installation

NEC 225.27

Underground feeders

24" burial depth, conduit required in most cases, warning tape recommended

Installation Standard

Feeder Sizing

NEC 225.39

Minimum size

Sized for calculated load, 60A minimum for dwellings over 80A main service

Load Capacity

Feeder Sizing Quick Reference

Service SizeFeeder WireEquipment GroundConduit SizeTypical Application
60A6 AWG Cu / 4 AWG Al10 AWG1.25"Small garage, basic loads
100A3 AWG Cu / 1 AWG Al8 AWG1.5"Standard garage, moderate loads
125A1 AWG Cu / 2/0 AWG Al8 AWG2"Large garage with EV charging
150A1/0 AWG Cu / 3/0 AWG Al6 AWG2"Workshop with heavy equipment
200A3/0 AWG Cu / 250 kcmil Al6 AWG2.5"Professional shop, welding

Voltage Drop Reference Table

Maximum current capacity for 5% voltage drop at 100ft run, 240V single-phase

Wire SizeResistanceAmpacity RatingMax Current (100ft)
10 AWG Cu1.24 Ω/1000ft30A24A (5% drop)
8 AWG Cu0.78 Ω/1000ft40A39A (5% drop)
6 AWG Cu0.49 Ω/1000ft55A62A (5% drop)
4 AWG Cu0.31 Ω/1000ft70A98A (5% drop)
3 AWG Cu0.25 Ω/1000ft85A122A (5% drop)
2 AWG Cu0.20 Ω/1000ft95A152A (5% drop)
1 AWG Cu0.15 Ω/1000ft110A203A (5% drop)
1/0 AWG Cu0.12 Ω/1000ft125A253A (5% drop)

Installation Cost Breakdown

Materials

$800-$3,500

Wire size, conduit, panel, disconnect

Trenching (100ft)

$600-$1,200

Depth, soil type, obstacles

Conduit Installation

$400-$800

Underground vs overhead, length

Panel Installation

$300-$600

Size, complexity, grounding

Inspection Fees

$150-$300

Local jurisdiction requirements

Total Project

$2,250-$6,400

Complete installation with permits

Note: Costs vary significantly by location, accessibility, and local labor rates. Always obtain multiple quotes from licensed electricians for accurate pricing.

Grounding System Requirements

Equipment Grounding Conductor

Requirement: Required with all feeders per NEC 225.30

Sizing: Table 250.122 - based on feeder OCPD rating

Installation: Run with feeder conductors in same raceway

Connection: Bonded to main panel ground and building ground rod

Grounding Electrode

Requirement: Required if no electrode exists at building

Sizing:

Installation:

Connection:

Bonding Requirements

Requirement: Metal parts connected to electrical system

Sizing:

Installation:

Connection:

Common Installation Mistakes

1

Undersized Equipment Ground

Consequence: Code violation, safety hazard

Correction: Size per Table 250.122 based on OCPD rating, not wire size

Repair Cost: Rewiring required - $500-$1,500

2

No Disconnect at Building

Consequence: Major code violation, failed inspection

Correction: Install listed disconnect switch at building entrance

Repair Cost: Disconnect + installation - $400-$800

3

Improper Burial Depth

Consequence: Safety hazard, code violation

Correction: Dig up and reinstall at proper depth (24" minimum)

Repair Cost: Re-excavation + labor - $800-$1,600

4

Multiple Neutrals in Panel

Consequence: Code violation, potential fire hazard

Correction: Separate neutral and ground bars in subpanel

Repair Cost: Panel modification - $200-$400

5

No Ground Rod at Building

Consequence: Incomplete grounding system

Correction: Install grounding electrode system per NEC 250

Repair Cost: Ground rod + connection - $150-$300

6

Voltage Drop Not Calculated

Consequence: Poor performance, equipment damage

Correction: Calculate drop, upsize wire if necessary

Repair Cost: Wire upgrade - $300-$1,200

Regional Code Variations

California

Requirements: Title 24 energy compliance, seismic considerations

Additions: EV-ready requirements, solar-ready provisions

Authority: CEC (California Electrical Code)

Florida

Requirements: Hurricane resistance, concrete encasement

Additions: Special flood zone requirements, corrosion protection

Authority: Local amendments to NEC

New York

Requirements: Frost depth considerations (4ft+), city permits

Additions: NYC has specific underground requirements

Authority: NYS Electrical Code + local amendments

Texas

Requirements: Heat considerations, expansive soil protection

Additions: Some areas require concrete encasement

Authority: NEC with local modifications

Minnesota

Requirements: Deep frost protection, heating considerations

Additions: Cold weather installation practices

Authority: Minnesota Electrical Code

Maintenance Schedule

Monthly

Visual inspection of disconnect and panel

Check for damage, corrosion, loose connections

Professional Required
Annually

GFCI testing (if present)

Test and reset all GFCI devices

Professional Required
Every 3 Years

Electrical connection inspection

Check panel connections, torque specifications

Professional Required
Every 5 Years

Ground system testing

Test grounding electrode resistance

Professional Required
Every 10 Years

Complete system inspection

Professional inspection of entire feeder system

Professional Required

Frequently Asked Questions

What size feeder do I need for a 100 amp garage subpanel?

For a 100A subpanel, you need 3 AWG copper or 1 AWG aluminum feeder conductors, sized for 100A continuous load. The equipment grounding conductor must be 8 AWG copper minimum per NEC Table 250.122. Always check voltage drop calculations for your specific run length.

Can I run a subpanel feeder overhead vs underground?

Yes, both overhead and underground feeders are allowed. Overhead requires minimum clearances per NEC 225.18 (10ft over driveways, 12ft residential). Underground requires 24" burial depth with proper conduit. Underground is often preferred for aesthetics and weather protection.

Do I need a separate ground rod for my detached garage?

If the building has no existing grounding electrode (ground rod, water pipe, etc.), then yes, you must install a grounding electrode system per NEC 250.32. This is in addition to the equipment grounding conductor run with the feeder.

What is the maximum distance for a garage subpanel feeder?

There is no NEC distance limit, but voltage drop becomes the limiting factor. For 100A loads, practical limits are typically 150-200 feet before wire upsizing becomes necessary to maintain acceptable voltage drop (3-5% maximum recommended).

Can I use the same feeder for garage and workshop loads?

Yes, you can size one feeder for combined loads using demand factors. Calculate the total demand load, apply appropriate demand factors per NEC Article 220, and size the feeder accordingly. A single disconnect can serve multiple buildings if properly sized.

What permits are required for garage subpanel installation?

Most jurisdictions require electrical permits for subpanel installation. The work typically requires inspection of the feeder installation, grounding system, and panel connections. Check with your local building department for specific requirements and fees.